This is the home page of the pool construction project
10/19/02
More excavation and removal of the old tree stumps to the wetlands area at the
back. Starting to take shape now - more work will be done in about a week with a
bulldozer.
click here for photos
10/18/02
Excavator is now working in the pool construction area, digging out the stumps and moving the large rocks
next to the brook to form a wall that will be the boundary of the new pool.
click here for photos
08/01/02
Things are going quite well... I have felled approx 15 trees, some really
large ones and some little tiddlers. Most of the time is spent debranching
and feeding the brush into the shredder. As the clearing takes shape, we are
getting more of an idea as to the shape of pool we want (more on that point
later). I feel confident enough to do all the construction work myself (am I
a fool or what?), I will hopefully be in a poision in a few weeks to rent a
backhoe/digger and start excavating the site, once I have the pool dimension
plans available. Site is a lot clearer now and brighter with some more of the
larger trees (70 feet +) felled...
click here for photos
07/01/02
Work starts on clearing an area of forest near the south-west corner of
the yard. Armed with a chainsaw, ropes and pulleys, wedges, sledgehammers,
a very large bowsaw and a very powerful shredder/wood chipper, I have
my work cut out...
click here for photos
Heavy construction machinery moves in...
|